Drill pads 2, 3 and 5 are complete.
The team continues to refine drill targets using results from the recent trenching program. Five trenches—1, 2, 3, 4 and 6—have been excavated and geologically logged.
Trenching has exposed numerous structures and faults, improving the geological team’s understanding of the project’s structural framework. These observations are being assessed alongside historical mine records and the Company’s 3D geological model to finalize drill-hole locations, evaluate targets and prioritize drilling.
Drilling mobilization is now expected in late November, revised from early November due to equipment availability.